Interdisciplinary Life Sciences Building (ILSB)
In collaboration with facility coordinators, the following adjustments have been made to the building:
- Calibrate sensors to modify Air Changes per Hour (ACH) according to AHSRAE Standards.
- Repaired all Enthalpy wheels, and revised the Enthalpy wheel control sequence to optimize energy performance.
- Repaired exhaust fan dampers that were causing fans to not reach setpoint and dampers that were found stuck in position.
- Repaired failed points for all fume hoods. Made mechanical modifications to 21 fume hoods to convert from CAV to VAV controls.
- Outdoor air control is now based off of classroom CO2 levels rather than hall CO2 levels.
- Modified Relief Air Flow Levels that were found to be set too high.
- Corrected synchronization issues by updating firmware on all Siemens field panels.
- Re-assigned sensors that were found to be crossed for different rooms.
| Commodity | Baseline Consumption | Actual Consumption | Avoided Consumption |
|---|---|---|---|
| Electricity (kWh) | 7,393,361 | 7,330,457 | $4,897 |
| Chilled Water (mmBtu) | 46,616 | 42,763 | $58,507 |
| Heating Hot Water (mmBtu) | 13,984 | 13,403 | $8,957 |
| Total Savings | $72,361 |